This PMP Sample Exam features 200 questions designed to assess and enhance your project management skills. It covers conflict resolution, project authorization, the triple constraint principle, and financial evaluation. Ideal for professionals seeking PMP certification.
The various management plans of the project
Schedule baseline and Cost baseline
Product configuration ID and Statement of work
WBS dictionary, WBS, Scope statement
Rate this question:
Reduce level of effort
Develop a training plan
Plan quality audits
Plan quality inspections
Rate this question:
…describes both the project scope and the product scope at detail level.
…authorizes the project and the use of organizational resources to meet project requirements.
…breaks down the project scope over several steps to describe the project on work package level.
…describes all activities which are necessary to create the project deliverables.
Rate this question:
Scope Statement
Network Logic Diagram
Work Breakdown Structure
Requested Change
Rate this question:
Requirements engineering
Communication planning
Formal procurements closure
Network diagramming
Rate this question:
Scope statement, WBS, and WBS dictionary
Cost baseline, Quality baseline and Schedule baseline
Configuration management plan and Configuration identification document
Procurement statement of work and Project scope statement
Rate this question:
…describes technical terms used for scope management.
…describes the details for each component in the WBS.
…translates essential WBS terms for global project teams.
…helps translating functional into technical requirements.
Rate this question:
Project charter
Team performance assessments
Cost baseline
Statement of work
Rate this question:
Responsible, Accountable, to be Consulted, to be Informed
Remote, Attached, Connected, Integrated
Risk Analysis and Caution Initiative
Randomly Accessible Cashflow Information
Rate this question:
To formally authorize a project or a phase and document initial requirements that satisfy the stakeholder’s needs and expectations.
To document how the project will be planned, executed, monitored/controlled, and closed.
To link the project, which is going to be planned, executed, and monitored/controlled to the ongoing work of the organization.
To describe the process of performing the work defined in the project management plan in order to achieve the project’s objectives.
Rate this question:
Three-point estimation
Triple constraint
Three wise men
Three needs theory
Rate this question:
A WBS
A schedule
A Project Scope Statement
A contract
Rate this question:
Project level performance reports
Activity level status reports
Stakeholder communication requirements
Responsibility assignments
Rate this question:
By observation and communication
Using closed questions during team meetings
Through third-party assessments
Through the team members’ functional managers
Rate this question:
Optimistic estimate
Most likely estimate
Budget estimate
Pessimistic estimate
Rate this question:
Co-location
Cross-functional dispersion
Virtual e-teams
Global team dispersion
Rate this question:
Resource histogram
Safety procedures
Recognition and rewards
Training needs
Rate this question:
... to have a strict standing in negotiating
... to show experience in tricking business partners
... to be team players and facilitators instead of "bosses"
... to be strongly linked to local traditions
Rate this question:
The sponsor manages the project
The sponsor provides funding for the project
The sponsor verifies that all of the work was completed
The sponsor negotiates all contracts
Rate this question:
Gold plating
Halo effect
Pre-assignment
Ground rules
Rate this question:
List of risk triggers
Risk register
Risk mitigation
Decision tree
Rate this question:
A requested change is always an opportunity to get more money paid by the customer and to secretly solve schedule and quality problems. You should make some reasonable estimates on time, costs, risks etc. and then add a nice margin on top of that to calculate the new price.
Customer satisfaction is your top priority. The customer gives you an opportunity to increase their satisfaction, which you should use to the maximum benefit. Most project managers have contingencies to cover risks; these can be used to pay the additional costs.
Before making a decision you should have a look at the customer’s parking lot. If you find there many expensive, new models, it is likely that you can use the requested change to increase the profit from the contract. Otherwise you should reject the request.
Handle the request according to the integrated change control processes described in your management plans. Then make a decision together with the appropriate change control body, whether the increased customer satisfaction will be worth the extra costs, work, risks etc.
Rate this question:
Claim
Trial
Refinement
Audit
Rate this question:
Informal Verbal
Formal Written
Formal Verbal
Informal Written
Rate this question:
Nominal group technique
Human resource assignment
Brainstorming
Decomposition
Rate this question:
A project team member
An attorney from your company’s competitor
A representative from your project team’s union
The project sponsors
Rate this question:
Confronting
Withdrawal
Smoothing
Forcing
Rate this question:
The cost of inspecting your product to be sure that it meets requirements.
The cost of reviewing documents used to produce your product to be sure that they do not have defects.
The cost of training your team on techniques that will help them avoid defects.
The cost of contracting another company to build part of the product.
Rate this question:
The authority level of the project manager
Detailed control account and work package descriptions
The business need that the project was undertaken to address
High-level risks
Rate this question:
Peer review
SWOT analysis
Delphi technique
Monetary value calculation
Rate this question:
Report performance
Verify scope
Perform integrated change control
Monitor and control risks
Rate this question:
Prototyping causes significant costs and should be avoided wherever possible.
They are tangible and allow for early feedback on requirements by stakeholders.
Prototypes are mostly developed toward the end of a design or build phase.
Prototypes increase the risk of misunderstandings between developers and users.
Rate this question:
Objectives specified in far more detail than necessary for a execution of a successful project.
Easily achievable objectives which help you reducing the pressure on yourself and the team.
Objectives that should be achieved in order to attain formal recognition by both the customer and the project sponsor.
Objectives that are described using specific, measurable, assignable, realistic and time-related specifications.
Rate this question:
Talk to your sponsor and try to get more resources assigned on similar conditions as the existing ones.
Talk with functional managers. Negotiate clear and written assignments with reliable scheduling priorities.
Ignore the difficulties, adjust your schedule and negotiate new deadlines according to the slower progress.
Focus on internal charges. Make sure that your project is not getting charged for more than the actual work.
Rate this question:
Storming from Forming, Storming, Norming, Performing
Panic from Enthusiasm, Panic, Hope, Solution
Kickoff from Assignment, Kickoff, Training, Communicating
Frustration from Direction, Frustration, Cooperation, Collaboration
Rate this question:
You should delay the payment also for 2 weeks.
You must immediately find a different contractor.
You should conduct a meeting with the contractor to resolve the delivery issues before making the payment.
You should make the payment and reschedule the project plan.
Rate this question:
Project Management Plan
Project Schedule
Work Breakdown Structure
Parametric Estimation
Rate this question:
Define Scope
Define Activities
Verify Scope
Control Scope
Rate this question:
Try to find some productive work for these staff members in the project and leave them on the team.
The best thing is to do nothing. The customer will not realize the problem anyway.
Try to find a responsible person for the over-assignment who can be made accountable.
Take the two people off the team immediately and arrange for the refund of the excess charges to the customer.
Rate this question:
A graph that is generated if a normal curve is integrated.
A graph that is to be integrated to generate a normal curve.
A metaphoric description of the short term uncertainties that are present in every project.
The graph that describes the typical growth of earned value during the course of the project.
Rate this question:
Which management fallacies can most easily be delegated to the worker?
How can discussion of the manager’s leadership style be avoided?
Has the employee been provided with sufficient instructions and work tools?
How can dispute related to unsatisfactory performance be avoided?
Rate this question:
Bidder conferences
Advertising
Qualified sellers list
Four-eyes meetings
Rate this question:
Theory X
Theory Y
Cost cutter
Effective
Rate this question:
...while the term resources is limited to equipment and materials.
...required for each activity in a work package.
...while the term resources is limited to human resources.
...to be obtained solely from the performing organization.
Rate this question:
…be in full control of the discussion and its outcomes.
…always take notes by herself.
…avoid a flip chart Parking lot.
…give guidance as required without interfering.
Rate this question:
Have her senior managers meet with the client to explain the situation
Hold a meeting with the client to figure out why he’s asking for the change
Do nothing; she’s the project manager, so she sets the rules
Have the client find more money for the budget
Rate this question:
Requirements Documentation
Scope Definition
Scope Dictionary
Project Scope Statement
Rate this question:
Accept the questions, but to be fair to everyone in the study group you should make sure everyone gets a copy
Refuse the offer, but encourage other study group members to make up their own minds
Refuse the offer, and report the person to your manager
Refuse the offer, and report the person to PMI
Rate this question:
Quiz Review Timeline (Updated): Mar 22, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.